Scope:
Engaged to support 8-day shutdown (tool time) to complete planned maintenance across the primary and secondary crushing circuits. Works included:
- Liner and hard skirt replacements
- Soft skirts replacements
- Dust mitigation works
- Change out of impact zones
- Support to belt crews
- Structural steel and chute repairs
- Drive replacements and lubrication change-outs
Solution:
Provide 2 experienced Supervisors and crew of 24 multi-disciplined trades, scaffold equipment and mechanical tooling container to execute shutdown works over the plant outage period.